New building for Highschool at “Steinerskolen in Hedmark”.
Designed and announced as a revolutionary pilot project:
- 100% solid wood in all loadbearing structures
- preheating / cooling of supply air via culvert in the ground
- 100% building materials from renewable resources
After obtaining a tender for the project, it became clear that costs for concrete work (especially all underground work in concrete) became so cost-driving that the project could not be carried out as planned. The building was therefore later built in conventional steel – concrete – wooden construction.